To identify the sequence of construction in more detail, the following headings are intended to highlight the manufactured items as they became used on site where an undercroft was used.
- Steel fabrication
- Roof decking
- Roof finishes, and rainwater gutters and downpipes.
- Floor slabs
- Oxford Method panels, cills, beam covers, fascias and doorframes.
- Undercroft drainage
- External doors
- Ceilings
- Floor screeds and coverings.
- Internal partitions and door frames. Internal glazed partitions and doors.
- Sanitary fittings
- Joinery fittings
The list has identified only the building requirements. Electrical and mechanical work was integrated within the programme.